The Wrap-up Meeting of the World Bank-funded Climate
Smart Irrigated Agriculture Project (CSIAP) commenced today at the Ministry of
Agriculture, Livestock, Lands and Irrigation (MALLI), bringing together senior
officials from the World Bank, the Ministry, and the CSIAP project team to
review the project’s implementation progress and finalize the next steps. The
meeting marks the conclusion of the World Bank Technical Support Mission held
from June 11–17, 2025. The session was chaired by Mr. D. P. Wickramasinghe,
Secretary of the Ministry, with the World Bank delegation led by Mr. Tomas
Ricardo Rosada Villamar (Practice Manager). Other key participants included Dr.
Sheu Salau (Task Team Leader – TTL), Thiruni Liyanage (Co-TTL and Senior Water
Resources Management Specialist), Dr. Athula Senaratne (Senior Agriculture
Specialist), Mr. Seenithamby Manoharan (Senior Consultant for Agriculture and
Rural Development), Mr. Jagath Seneviratne (Consultant for Monitoring &
Evaluation), and Mr. Sanjeewa Rodrigo (Consultant for Agribusiness &
Marketing).
Purpose of the Wrap-Up Meeting
The wrap-up meeting marks the culmination of a World
Bank Technical Mission or project review, serving several vital functions:
- Presentation of Mission Findings: The World Bank
team shared preliminary findings, assessments, and recommendations from their
mission.
- Review of Project Progress: Achievements,
challenges, and the status of project components were discussed in detail.
- Discussion of Agreed Actions: A list of agreed
actions was finalized for implementation before project closure.
- Stakeholder Engagement: The meeting provided a
platform for active engagement among Ministry officials, World Bank
representatives, and project staff.
Project Achievements and Next StepsDr. Sheu Salau announced that the CSIAP has been
honored with the prestigious South Asia Vice President’s Award this
year, congratulating the entire team on this outstanding achievement.
Looking ahead, under Phase II of CSIAP, 173 tanks
are scheduled for rehabilitation in 2025. Of these, 15 tanks may see work
extend beyond December if rainfall exceeds expectations. All tanks are
currently under rehabilitation, with Dr. Salau confirming that the required
funds are fully committed and no cancellations are anticipated during the
current mission.
Agreed Actions and Strategy
The following key
actions and strategies were agreed upon:- Complete
Procurement: All RFQ items and related activities to be completed by July
30, 2025.
-
Utilize GOSL Funds: Any operational cost increases beyond committed IDA
funds will be covered by the Government of Sri Lanka funds.
-
Minimize Variation Orders: Avoid or minimize VOs; if necessary, VOs must
be proactively issued by DPD offices in consultation with DAD and PID by July
31, 2025.
-
Finalize Training: All planned training activities (worth USD 0.72
million) to be completed by November 30, 2025.
-
Monthly Billing: Contractors to ensure monthly submission of bills.
-
Additional Support: DAD and PID will receive extra support for suspension
handling and bill processing through two consultations (2 days per week), and a
vehicle will be hired at each DPD office until October 31, 2025.
The meeting was also
attended by Ms. Anuradha Dharmasena (Director, Development, MALLI), Mr. Saman
Bandulasena (Project Director), as well as specialists and officers of the
CSIAP.
Story by: Ms. Sharmila Shanmuganthan, Social
Safeguard and Gender Development Officer, PMU, CSIAP
Photograph by: Ms. Gayani Dassanayake, PMU-CSIAP
Posted by CSIAP Sri Lanka Read full article Published Date : 2025-06-17